News & Insight

Case law June 13, 2019
When and how to warrant financial projections… High Court provides guidance in Triumph Controls case

When and how to warrant financial projections… High Court provides guidance in Triumph Controls case

Be careful when warranting forward-looking projections.

In Triumph Controls – v – UK Ltd & Anor v Primus International Holding Company & Ors [2019] EWHC 565 (TCC), the claimants were the subsidiaries of Triumph Group, Inc. (“Triumph”). Triumph is a multinational aerospace and defence manufacturer and service provider based in the United States.

The defendants – the ‘Sellers’ – were subsidiaries of Precision Castparts Corporation (“Primus”). The Primus group is a multinational manufacturer of complex metal components for the aerospace industry.

On 27 March 2013, Triumph and Primus entered into a share purchase agreement (the “SPA”) by which Triumph purchased the share capital of three Primus subsidiaries. The consideration paid by Primus under the SPA was US$ 76,530,145.

Two subsidiaries were based in Thailand and the third was based in Farnborough (“Farnborough”). Farnborough was operating its business under the National Aerospace and Defence Contractors Accreditation Program (“Nadcap”).

Following the acquisition, Triumph discovered a significant shortfall in the Primus’ expected revenue. This was due to the operational issues and delivery arrears at Farnborough which led to Primus reporting a significantly worse financial performance than forecast in various documents. Consequently, in December 2013, following a Nadcap audit, Farnborough lost its Nadcap accreditation.

Primus remained in debt despite Triumph having provided extra financial assistance. As a result, the Primus shares were “worthless”.

The SPA contained a number of operational and financial warranties.  Triumph sought damages limited to US$ 63,530,145 against Primus for breach of these warranties.

The FLP warranty

One of those warranties is the subject of this piece, and it read as follows:

So far as the Sellers are aware, the forward-looking projections relating to the Companies have been honestly and carefully prepared”.

We have added the underlined emphasis so as to segment the warranty.  Each segment was addressed as follows below.

“So far as the Sellers are aware…”

The SPA defined the Sellers’ awareness as follows:

…the actual knowledge of the Sellers after they have made all reasonable enquiries of [five named individuals], who shall themselves have made due and careful enquiries in respect of the aspects of the business of the [target companies] for which they are respectively responsible”.

The Court decided that the Sellers were deemed to have knowledge of the errors in the financial projections.

Meaning of “forward-looking projections”

The SPA did not define “forward-looking projections” and as a consequence Triumph cited quite a number of documents within the data room as containing forward-looking projections.  The list of documentation was not disputed by Primus.

Had Primus had the opportunity to revise the language in the SPA, however, one wonders whether they would have defined “forward-looking projections” to include a narrower set of documents.  (Certainly, when on the sell- or investee-side of transactions you would always want to agree what any such projections actually were and on which the warranty bites.)

Meaning of “honestly and carefully prepared”

The term “honestly and carefully prepared” was also not defined in the SPA.  Dishonesty was not at issue and so it was the meaning of the term “carefully” that was considered.

The Court’s view was as follows:

The plain and natural meaning of the words used is that the forward looking projections were warranted to have been prepared with care by those who had the required skills and knowledge. Primus did not warrant accuracy, only careful preparation.”

The Experts agree that “carefully prepared” is not a recognised accounting term and that there is no accounting standard or guidance that provides definitive information as to what would constitute a “carefully prepared” forecast. In the absence of any accounting definition, the Experts agree that the assessment of whether a forecast wasnot carefully prepared” is a matter of judgement based on professional experience”.

Judgment on the facts

The Court concluded that the forward looking projections failed to take into account, properly or accurately, key operational and financial assumptions such as the requirement for buffer stock to be built, the requirement for arrears to be reduced, increased labour and scrap costs during accelerated production and the consequential delay to production in Thailand.  At one point the model seems to have been updated – disastrously it would turn out – without updating the underlying assumptions.

The forward-looking projections failed to adequately model the known operational and financial position of the Primus companies as at October 2012.  There was a lack of careful preparation.  This was a breach of warranty from which Triumph had suffered a loss as the purchase price was put forward on the basis of the projections.

Triumph, therefore, succeeded in its claim.

Quantum – calculating the value of damages

The Court applied the principle that damages for breach of contract are intended to put a claimant in the position in which it would have been if the defendant had complied with the terms of the contract.

The damages to be awarded were therefore valued at the difference between the purchase price paid and the price that would have been paid had the projections been carefully prepared.

The Court then considered testimony from the expert witnesses as to what the financial projections should have said had they been “carefully prepared”.  There are many ways to value a company and the experts had looked at the net asset values, a valuation of cash flows discounted for risk and then valuations of similar businesses in the market.  The Court went with the discounted cash flow approach.

Putting this into practice on deals

Those two words – “carefully prepared” – ended up creating quite the volume of work for claimant and defendant, for their legal counsel and advisors, for their expert witnesses and for the Court.  The costs involved and time expended were presumably somewhat eye-watering.

The case serves as a cautionary tale as regards giving warranties as regards financial projections or any other type of forward-looking statement.  Warranties are contractual promises as regards the truth of a certain state of affairs – if that state of affairs is in the future then anyone warranting as to its accuracy leaves itself a hostage to fortune.

Acting for anyone giving a warranty as regards the “careful preparation” of financial projections, assuming that it can’t be negotiated out, we would usually advise as follows:

  • Be very clear about which set of projections the warranty bites on. By using a defined term, avoid the Primus scenario outlined above where you potentially have the buyer rooting around in a data room looking for anything forward looking to put forward as the basis for a warranty claim.
  • Be clear as to how the business is being valued? A net asset calculation, discounted cash flows, a multiple of EBITDA?
  • Are the assumptions in the projections accurate? Are all the relevant assumptions in there?  Have the assumptions been updated with the latest information?  Do the latest management accounts tally in terms of being the start point for the model?
  • Document the basis on which those assumptions are made.
  • Do the projections map out a suitably widely scoped worst case scenario?  Stuff happens.
  • Have the accountants reviewed the projections? Has the whole management team reviewed the projections?
  • Have management sat down with the buyer and talked it through the projections and updated the model in the light of feedback?
  • Have management looked at the market more widely and whether their assumptions and methodologies are consistent with market practice (and if not documented why that is)?
  • Is the model ‘live’ and being updated by management as the deal proceeds to completion? It appears that the Primus model suffered badly from not being updated.
  • Never warrant as to “accuracy” of forecasts or predictions – there is a world of possibility out there and most budgets don’t end up tracking what actually happens!

If you would like to discuss more about this case, or about warranties in general, then do please contact us at enquiries@humphreys.law.

This piece was researched and prepared by Henry Humphreys and Amir Kursun from our Transactional team.

Humphreys Law

If you would like to contact a member of our team, please get in touch by filling in the form below.

"*" indicates required fields

Humphreys Law